The longest chain of dependent tasks sets the floor on how fast everything can finish: speeding up anything else changes nothing.
Picture a project as a graph of tasks. Some tasks can't start until others are done: you can't paint a wall before it's built. Each task takes some time. Lay the dependencies out as arrows and you get a directed acyclic graph (DAG): arrows only point forward, never in a loop.
The whole project can't finish until its slowest chain of dependencies is done. That chain, the critical path, is the longest weighted path through the DAG. Its length is the minimum possible finish time. Every task on it has zero slack: delay one and the whole project slips. Tasks off the path have spare room, so rushing them buys you nothing.
Process nodes in topological order so every predecessor is computed before the node that needs it. Each task's earliest finish is its own duration plus the latest of its predecessors' finishes: max over preds, not sum. The project finish is the largest finish of all. A backward pass gives each task a latest finish; slack = LF − EF, and the zero-slack chain is the critical path.
for v in topo_order(G): # preds done first
EF[v] = dur[v] + max([EF[u] for u in preds[v]], default=0)
finish = max(EF.values()) # project finish time
# backward pass for slack
for v in reverse(topo_order(G)):
LF[v] = min([LF[w] - dur[w] for w in succs[v]], default=finish)
slack[v] = LF[v] - EF[v]
# critical path = the chain of tasks where slack == 0
| Operation | Cost | Why |
|---|---|---|
| Topological sort | O(V + E) | Visit each task and each dependency edge once |
| Forward + backward pass | O(V + E) | One DP sweep over the sorted order; each edge relaxed once |
| Whole critical path | O(V + E) | Longest path on a DAG is linear: the topo order removes the hard cases |
| Brute-force longest path | exponential | Enumerating every source-to-sink path explodes; on a general graph longest path is NP-hard |
max over predecessor finishes, never a sum.Six tasks with durations and dependencies. A(3) starts the project; B(2) and C(4) both need A; D(4) needs both B and C; E(3) needs C; F(2) needs both D and E. Run the forward pass in topological order: EF_A = 3, EF_B = 3 + 2 = 5, EF_C = 3 + 4 = 7, EF_D = max(EF_B=5, EF_C=7) + 4 = 11, EF_E = 7 + 3 = 10, EF_F = max(EF_D=11, EF_E=10) + 2 = 13. The project finishes at 13. Backtracking the zero-slack chain gives A → C → D → F. B has 2 units of slack and E has 1: you could start either late without slipping the project.
The interactive graph above is a 7-task variant (it adds a final task G); the logic and the readout are identical.
In the worked example, task B has 2 units of slack. If your team finds a way to finish B one day faster, what happens to the project finish time of 13?
Coach note: if this didn't click yet, replay the visual and watch which nodes stay lit at the end. Only those, the zero-slack chain, move the finish line when you change them.